Mesfin Industrial Engineering PLC intends to outsource construction Conversion of ESP to Bagfilter in messebo as per the attached bill of Quantity and specification
  • Posted Date: Tuesday 26th, April 2016 (over 8 years ago)
  • Closing Date: Tuesday 03rd, May 2016 12:00 am (closed)
  • Bid Bond:100000.00
  • location: Mekelle
  • Bid Document Price:100.00
  • Bid Opening Date: Tuesday 03rd of May 2016 12:00 am
  • House & Building Construction/
  • Print
  • Pdf

1 MIE now invites registered contractors of Grade GC -5 , BC- 5 and above with in the following criteria

2 Renewed trade license for the year 2008 EC , VAT registration certificate and have Tax identification NumberÂ

3 Tender documentation can be bought with un-returnable 100 Birr from MIE Supply Department at any working time from 22/04 2016 2:00 morning local time upto 3/05/2008 6:00 local time.

4 Â Bid security in the form of CPO Birr 100,000 (one hundred Thousand Birr only) is required

5 Sub-contractor is Prohibited

6 Price shall include all cost relating to customs duties taxes, fees and less payable by the Tenderer

7 The tender shall complete the pricing sheet attached in BOQ of the tender document

8 One original and one copy technical and financial document is required

9 Final data of submission of the financial and technical document is 03/05/2016 at 8:00 local time

10 Tender will be opened at MIE compound in 03/05/2016 at the same date 8:30 local time

11 Delivery period for the project is 55 calendar days including mobilization and mobilization after site hand overÂ

12 Bidder are strongly advised to visit the site

13 The bidder shall construct a temporary store that can store 400qtl cement

14 Any bidder shall participate in only one bid if the bidder has participate in more than one bid the bid will be rejected

15 only Cement is to be provided by the MIE PLC

16 Every required material, labour , machine and tools is to be provided by the bidder except Cement and rebar

17 No claim whatsoever entertained will be arising Tenderers failure to study the tender documents

18 Failure to comply with above submission procedure may invalidate the tender

19 MIE has the right to cancel the tender any time Â

Backs